Project Overview

A better experience for public transport customers on the Blue Mountains line.

The Glenbrook Station Upgrade is part of the NSW Government initiative to improve accessibility within the Transport Access Program. The program initiative is to provide a better experience for public transport customers by delivering accessible, modern, safe, and integrated transport infrastructure.

Scope of Works

Station Works

  • Platform works — lift base, pit and shaft up to footbridge level
  • Platform slab reinstatement (possession works)
  • Platform regrading (possession works)
  • Padmount substation
  • New pedestrian ramp on Buffit Parade
  • Strip footings, retaining walls and stairs
  • Precast ramp works (cast on site)
  • All concrete quality as per RMS QA specification B80
Project Facts
Client
Downer EDI Works
Sector
Railway Stations
Location
Glenbrook, NSW
Status
Completed
Duration
March 2019 – December 2019
Specification
RMS QA B80
Program
Transport Access Program